FCA Proposals for BRO Roads, Shinkula Tunnel and Development Projects Reviewed in Keylong.
DC Nivedita Negi directs departments and user agencies to expedite pending formalities, EDS replies and compensatory payments.
Shimla:
Deputy Commissioner Lahaul-Spiti Nivedita Negi on Friday reviewed the progress of Forest Conservation Act (FCA) proposals related to various developmental projects, road infrastructure works of the Border Roads Organisation (BRO) and projects being undertaken by Project Yojak, directing concerned departments and user agencies to expedite pending formalities for their early disposal.
The review meeting was held at the conference room of the Deputy Commissioner’s office in Keylong, where the status of departmental proposals under the Lahaul Forest Division, BRO road and construction projects, and Project Yojak proposals was discussed in detail. The meeting also reviewed the action taken on issues raised and directions issued during the previous meeting.
During the meeting, proposals pending on the PARIVESH portal were reviewed, including those related to Government Polytechnic Udaipur, Eklavya Model Residential School Kukumseri and the Udaipur substation. Matters concerning the CSIR-IHBT centre at Tandi, Phunkyar helipad, dredging work at Jahalma Nala and Raja Ghepan cricket ground and winter sports complex at Sissu were also discussed.
The Deputy Commissioner reviewed four proposals associated with BRO’s 94 RCC and 38 BRTF, including improvement and widening works on the Sumdo-Kaza-Gramphu and Sansari-Kilad-Tindi roads. The meeting also discussed the approval of a 14.9-hectare Forest Conservation Act proposal for the improvement and widening of the Manali-Sarchu road, along with the status of other proposals related to parking facilities and roadside infrastructure.
Proposals under Project Yojak concerning the construction of the Shinkula Tunnel and its approach road were also examined. The review included FCA proposals for satellite offices, residential facilities and other temporary construction infrastructure. Officials were directed to complete pending compensatory payments and other required formalities.
Nivedita Negi directed the concerned departments and user agencies to submit replies to pending Essential Details Sought (EDS), Stage-I compliance reports and compensatory payments at the earliest. She emphasised that the Forest Department should ensure timely scrutiny and processing of proposals to avoid unnecessary delays.
The progress of forest and wildlife clearance cases submitted by the Spiti Wildlife Division, Kaza, was also reviewed in detail. Officials discussed major bottlenecks affecting the processing of proposals. The Forest Department informed the meeting that coordination had been undertaken with various forest divisions to arrange land for compensatory afforestation and that relevant proposals had been forwarded through the PARIVESH portal.
The Deputy Commissioner directed all concerned agencies to regularly monitor pending cases and ensure timely submission of required documents so that forest clearance proposals could be processed and disposed of without unnecessary delays.
The meeting was attended by Divisional Forest Officer Indrajeet Sirra, Project Officer Ashwani Kumar, SDM Kunika Akers, BRO officials and representatives of various departments.
Officials from the Kaza subdivision, including ACF Chaman Thakur, SDM, BRO and ITBP representatives, also participated in the meeting through virtual mode.